Question: A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative
A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CP) as that incurred by the pryect to dete As of now The oled vale (EV) a 185 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day. What is the estimate at completion (EAC)? 310 person/day 334 person/day 315 person/day 285 person/day