Question: A large construction job will take 4 years to complete. The costs of the many required inspections can be reduced by purchasing a voice recognition

A large construction job will take 4 years to complete. The costs of the
many required inspections can be reduced by purchasing a voice recognition
system to act as the front end for a word processor. Then, inspectors
can be trained to record their comments and revise the written output of
an automated form.
The firms interest rate is 12%. What is the PW of the cash flows for the
voice recognition system? The first cost for purchase and training is
$100K. Savings are estimated at $30K, $40K, $65K, and $35K for the 4 years
of construction.