Question: A large warehouse project requires 3 0 , 0 0 0 cubic yards of excavation ( cut ) and 2 4 , 0 0 0
A large warehouse project requires cubic yards of excavation cut and
cubic yards of fill. The in situ soil density is pcf and the in situ water content is
The fill soil is to be compacted to relative compaction, and its maximum dry density
is pcf assume the fill has a uniform dry density that is of the maximum
a Determine how much excess cutfill soil the project will generate. Report your
answer as a mass of solids.
b When soil is placed in a dump truck for transportation it takes up more
volume than it does in situ. If a dump truck can transport cubic yards of soil
per trip, how many trips will be needed to remove all of the cut soil?
c During transportation, the cut soil loses moisture such that it arrives at the fill area
with a moisture content of If the soil is to be compacted at a moisture
content of how much water will need to be added to the soil to compact the
entire fill area?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock