Question: A limestone formation, with an average depth of 5 ft is exposed over the full 8 0 - ft width and 2 3 , 7
A limestone formation, with an average depth of ft is exposed over the full ft width and ft length of a highway cut. Preliminary seismic investigations indicate that the rock layer has a seismic velocity of fps The contractor proposes to loosen this rock by using a singleshank ripper on a power shift, tracktype tractor.
The job conditions relative to lamination and other rock characteristics are average, or midway between adverse and ideal. A min hour working efficiency is possible. The contractor wishes to explore the use of two DT Caterpillar dozers with single shankfor performance data see the CAT Handbook posted on Blackboard and check the assumptions
O&O cost for these tractors is $ per hour including rippers. However, dozers in ripping applications increase O&O cost The operator's wage & benefits is $ per hour.
What is the project duration with two dozers hour work days Round answer to nearest WHOLE days.
What is the costbcy to rip this rock?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock