Question: A line process at a manufacturing plant contains three workstations, A , B , and C in sequence A - B - C . The

A line process at a manufacturing plant contains three workstations, A, B, and C in sequence A-B-C. The average production capacity at each station is as follows:
Station A: 52 parts per hour; Station B: 18 parts per hour; Station C: 37 parts per hour
Management suggests that new equipment be purchased to increase the capacity of Station C so that it can produce 60 parts per hour, which is also the demand rate for the parts. What is your response?