Question: A linear programming computer package is needed. straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs

A linear programming computer package is needed.
straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs per unit are shown.
departments are as follows.
SP= number of supports purchased, TM= number of straps manufactured, and TP= number of straps purchased. Express time in minutes per unit.)
Min
Cutting constraint
Milling constraint
Shaping constraint
Frame constraint
The photo is cut off. Here's Everything else "Strap constraint
FM, FP, SM, SP, TM, TP >=0
How many of each component should be manufactured and how many should be purchased? (Round your answers to the nearest whole number.)
(FM, FP, SM, SP, TM, TP)=
(b)
What is the total cost (in $) of the manufacturing and purchasing plan?
$
(c)
How many hours of production time are used in each department? (Round your answers to two decimal places.)
Cutting
hrs
Milling
hrs
Shaping
hrs
(d)
How much (in $) should Frandec be willing to pay for an additional hour of time in the shaping department?
$
(e)
Another manufacturer has offered to sell frames to Frandec for $45 each. Could Frandec improve its position by pursuing this opportunity? Why or why not? (Round your answer to three decimal places.)
---Select---
. The reduced cost of
indicates that the solution
---Select---
be improved."
 A linear programming computer package is needed. straps may be either

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!