Question: A linear programming computer package is needed. the cherry cabinets, the number of hours available for the final finishing operation, and the cost per hour
A linear programming computer package is needed.
the cherry cabinets, the number of hours available for the final finishing operation, and the cost per hour to perform the work are shown here.
of the cherry cabinets if it worked only on cherry cabinets.
cabinetmaker and percentage of cherry cabinets assigned to cabinetmaker
Min
st
hours available
hours available
hours available
oak
cherry
completing both projects? Round your percentage values to one decimal place.
c If Cabinetmaker has additional hours available, would the optimal solution change? Explain.
Yes, each additional hour of time for cabinetmaker will reduce the total cost by $ per hour.
Yes, each additional hour of time for cabinetmaker will reduce the total cost by $ per hour.
No cabinetmaker has a slack of hours, so increasing cabinetmaker s time will not reduce costs.
No cabinetmaker has a slack of hours, so increasing cabinetmaker s time will not reduce costs.
d If Cabinetmaker has additional hours available, would the optimal solution change? Explain.
Yes, each additional hour of time for cabinetmaker will reduce the total cost by $ per hour.
Yes, each additional hour of time for cabinetmaker will reduce the total cost by $ per hour.
No cabinetmaker has a slack of hours, so increasing cabinetmaker s time will not reduce costs.
No cabinetmaker has a slack of hours, so increasing cabinetmaker s time will not reduce costs.
e Suppose Cabinetmaker reduced its cost to $ per hour. What effect would this change have on the optimal solution? Explain.
The new objective function coefficients for and are and respectively. The optimal solution
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock