Question: a. Loading machine standard time=0.55 minute b. Unloading machine standard time=0.35 minute c. Walk-time between two machines= 0.10 minute d. Power-feed time (machine time) =1.60
a. Loading machine standard time=0.55 minute
b. Unloading machine standard time=0.35 minute
c. Walk-time between two machines= 0.10 minute
d. Power-feed time (machine time) =1.60 minute
e. Operator rate=18$/hr
f. Machine rate=15$/hr
Draw an operator machine chart for the optimal solution.