Question: A loan processing operation that processes an average of 4 loans per day. The operation has a design capacity of 1 5 loans per day

A loan processing operation that processes an average of 4 loans per day. The operation has a design capacity of 15 loans per day and an effective capacity of 8 loans per day. What is the utilization at effective capacity?