Question: A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and
A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day.
- Calculate the Utilization
b. Calculate the Efficiency