Question: A local project being analyzed by PERT has 13 activities, 6 of which are on the critica path. If the estimated time along the critical
A local project being analyzed by PERT has 13 activities, 6 of which are on the critica path. If the estimated time along the critical path is 105 days with a project variance of 25what is the probability that the project will be completed in 100 days or less? (please answer to four decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts