Question: A local project being analyzed by PERT has 14 activities, 6 of which are on the critical path. If the estimated time along the critical
A local project being analyzed by PERT has 14 activities, 6 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 100 days or less? (please answer to four decimal places) Your Answer: Your