Question: a m Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (0) b A 31 40 49 B 44 50 56 48 60

a m Time estimates Expected Variance Activity
a m Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (0) b A 31 40 49 B 44 50 56 48 60 72 D 22 31 34 Start End B D What is the estimated variance in the time for Activity C