A machine cell uses 220 pounds of a certain material each day. Material is transported in vats that hold 15.0 pounds each.
Cycle time for the vats is about 1.6 hours. The manager has assigned an inefficiency factor of 0.05 to the cell. The plant operates on an 8 hour day.
How many vats will be used?