Question: A major change in scope, requested by the owner, will cause the project s budget and the contract completion date to be exceeded, even though
A major change in scope, requested by the owner, will cause the projects budget and the contract completion date to be exceeded, even though the owner has emphatically told you that no additional cost or time will be authorized. What should the CM do
Work with the designer and contractor to try to identify cost and time saving alternatives and present the options to the owner
Get the Contracting Officer to issue the least cost option to the contract
Tell the owner hes crazy and it cant be done
Issue a change order immediately