Question: A major change in scope, requested by the owner, will cause the project s budget and the contract completion date to be exceeded, even though

A major change in scope, requested by the owner, will cause the projects budget and the contract completion date to be exceeded, even though the owner has emphatically told you that no additional cost or time will be authorized. What should the CM do?
Work with the designer and contractor to try to identify cost and time saving alternatives and present the options to the owner
Get the Contracting Officer to issue the least cost option to the contract
Tell the owner hes crazy and it cant be done
Issue a change order immediately

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!