Question: A man worked to construct a bridge. The first unit took 10 hours with a 70% learning curve. The third unit should take how many
A man worked to construct a bridge. The first unit took 10 hours with a 70% learning curve. The third unit should take how many hours?
a. 6.2
b. 7.0
c. 5.7
d. 4.7
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts