Question: A manager has just received a revised price schedule from a vendor as below. Annual Demand is 120 units, ordering cost is $8, and annual
A manager has just received a revised price schedule from a vendor as below. Annual Demand is 120 units, ordering cost is $8, and annual carrying cost is $1 per unit. What is the minimum total cost that the manager can achieve?
Quantity | Unit Price |
1 to 39 units | $14 |
40 to 59 units | $13 |
60 to 89 units | $12 |
90 or more units | $11 |
Step by Step Solution
There are 3 Steps involved in it