Question: A manager wanted to predict how much rework time would result from taking a manufacturing line from producing 8 hours a day to 24 hours
A manager wanted to predict how much rework time would result from taking a manufacturing line from producing 8 hours a day to 24 hours a day. The manager carefully analyzed three years of performance from manufacturing lines that operated 8 hours a day to make the prediction. The manager is at risk of making what type of error?
| a | Data overfitting error. | |
| b | Extrapolation beyond the range error. | |
| c | Either a type I or type II error |