Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: a. In order of most following tasks. Tiebreaker: greatest positional weight. b. In order of greatest positional weight. Tiebreaker: most following tasks. c. What is the efficiency? 3 2 4 a b C 7 4 e d 5 6 f g A producer of inkiet print 9 5 h