Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 3 0 units. Assume the shop works

A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 30 units. Assume the shop works a 58-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: What is Efficiency?
Note: Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.
. In order of greatest positional weight. Tiebreaker: most following tasks.
Note: Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h
in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.
What is Efficiency?
Note: Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.
a. What is Cycle time?
Note: Round your answer to 1 decimal place.
Cycle time; ______ minutes
In order of most following tasks. Tiebreaker: greatest positional weight.
Note: Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place. What is Efficiency?
Note: Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place. Efficency ___%
b. In order of greatest positional weight. Tiebreaker: most following tasks. Note: Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.
What is Efficiency?
Note: Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place. Efficiency ___%
 A manager wants to assign tasks to workstations as efficiently as

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!