Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 4 units. The department uses a working

A manager wants to assign tasks to workstations as efficiently as possibleA manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 4 units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:

a. In order of most following tasks. Tiebreaker: greatest positional weight.

b. In order of greatest positional weight. Tiebreaker: most following tasks.

c. What is the efficiency? (Round your answer to 2 decimal places.)

a. In order of most following tasks. Tiebreaker: greatest positional weight. b. In order of greatest positional weight. Tiebreaker: most following tasks. a. In order of most following tasks. Tiebreaker: greatest positional weight. b. In order of greatest positional weight. Tiebreaker: most following tasks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!