Question: A manufacturing company implementing JIT has a target production rate of 1 0 . 0 0 0 units per month. The company operates 2 5

A manufacturing company implementing JIT has a target production rate of 10.000 units per month. The company operates 25 working days a month with single shift (8 hours) each day. The company produces three different models X, Y and Z and their sales distribution are %20 X,%20 Y and %60 Z. What is the production sequence?
Z-X-Z-Y-Z-Z-X-Z-Y-Z
Z-Z-X-Y-Z-Z-X-Y
Z-X-Y-Z-X-Y
X-Z-Y-Z-X-Z-Y-Z