Question: A manufacturing facility needs the raw material (A, B, C and D) to undergo two processes, grinding and deburring. The estimated job time required (in

A manufacturing facility needs the raw material (A, B, C and D) to undergo two processes, grinding and deburring. The estimated job time required (in hours) are detailed below. Process A B C D Grinding 4 7 9 5 Deburring 2 8 6 7 Question 7 (2 points) Determine the make-span. Question 7 options: a) 6 hours b) 9 hours c) 29 hours d) 32 hours