Question: A manufacturing facility needs to open a new assembly line in four months or there will be significant cost overruns. The manager of this project

A manufacturing facility needs to open a new assembly line in four months or there will be significant cost overruns. The manager of this project believes that there are four possible values for the random variable X: 2.5, 3, 4, and 5. It is currently believed that the probabilities of these four possibilities are in the ratio 1 to 2 to 2 to 3. That is, X = 3 is twice as likely as X = 2.5 and X = 5 is 1.5 times as likely as X = 4.

(1) Find the probability distribution of X. (Use appropriate mathematical expressions wherever you can to answer this question.) (2 points)

(2) What is the probability that this project will be completed in at least 3 months from now? (2 points)

(3) What is the probability that this project will not be completed on time? (2 points)

(4) What is the expected completion time (in months) from now for this project? (3 points)

(5) How much variability (in months) exists around the expected value found in question (4)? Give both the variance and standard deviation. (3 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!