Question: A manufacturing process consists of three sequential operations that can work independently. Operation A takes 2 hours per unit of product, Operation B takes 3
A manufacturing process consists of three sequential operations that can work independently. Operation A takes hours per unit of product, Operation B takes hours, and Operation C takes hours. On average and under steady state assumption, how long does it take to produce one unit of product?
Group of answer choices
hours
hours
hours
hours
Step by Step Solution