Question: A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors. What should the risk manager do to evaluate and select the best option based on costs and probabilities? Conduct a sensitivity analysis Perform a FMECA fault tree analysis Conduct an analytic hierarchy process Perform a decision tree analysis