Question: A Metropolitan district is considering three alternative designs (D1, D2, D3) for a major water infrastructure project with a projected economic life of 15 years

A Metropolitan district is considering three alternative designs (D1, D2, D3) for a major water infrastructure project with a projected economic life of 15 years and interest rate of 8.5% per annum.

For each option, the Table below shows the construction cost (CT), annual maintenance and operating cost (MC) and annual net benefits (B) to the host and nearby communities. Given that the options are mutually exclusive, use cost-benefit analysis to establish which option should be built.

Confirm your answer using NPV scores.

Options

CT

( million)

MC

( million)

B

( million)

D1

7.5

0.111

2.13

D2

8.4

0.125

2.45

D3

9.3

0.205

2.53

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!