Question: A mine with an open pit: Upper radius: 800 m Base radius: 150 m Heigh: 200 m The mine must be pushed back 50 m
A mine with an open pit:
Upper radius: 800 m
Base radius: 150 m
Heigh: 200 m
The mine must be pushed back 50 m back to extract more materials, if the rock density is 3.2 g/cm3 and the price to truck the rock is $3.00 per tonne. What's the total cost of the excavation?
How many tonnes of copper could be recovered if the volume of the frustum of a cone =
and the strip ratio is 0.75 and the ore is 1.5% copper.
31h(a2+b2+ab)