Question: A mini project was estimated to cost $ 2 5 , 0 0 0 and to be completed on 1 5 December 2 0 0
A mini project was estimated to cost $ and to be completed on December The calculated actual cost at the end of September is $ The remaining percent work is to be completed as soon as possible to maintain the completion due date. a What are the cost and schedule variances at this stage? marks
b If the original project duration was months and total budget was $ Calculate the estimated cost of completion and estimated time to complete. marks
c Comment on how well the project is doing in terms of time and cost. marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
