Question: A mining company is planning to develop an open - pit limestone mine and will use a Volvo EC 6 5 0 ME excavator along

A mining company is planning to develop an open-pit limestone mine and will use a
Volvo EC 650 ME excavator along with Volvo A25D mechanical drive rear dump haul
trucks for ore extraction. The truck's capacity is 15Bm3, which will be loaded with
limestone classified as excavation class 5. The material has a swell factor of 1.3, and the
bank density is 2,200kgBm3. The trucks will operate on the same level as the excavator.
The excavator's bucket has a capacity of 4.4m3 with a fill factor of 0.75, and it is
operated by an experienced operator. The loader operates at a rate of 550Lm3hr. The
loading time for the first bucket is 0.15 minutes, and 0.4 minutes for subsequent passes.
The haul distance from the excavation site to the processing plant is 2.4 km , with the
following details:
Note: For travel time through curves, if the radius is more than 50 m , refer to line 5 for
calculations.
The trucks will spend an average of 1.4 minutes maneuvering and dumping at the
processing plant. The spot time at the excavator is 12 seconds, with an additional 0.35
minutes allocated for other planned activities. Unavoidable job delays are expected to
average 1.55 minutes per cycle.
What is the estimated hourly production of a truck?
Determine the number of trucks required for the ore handling fleet.
Given that the hourly operating costs are $140/hour for the loader (with operator)
and $110/hour for the truck (with operator), calculate the unit costs.
Provide detailed calculations, the necessary highlighted charts and update the site
form as required.
Compare the results if Volvo A30D mechanical drive rear dump haul trucks with
a capacity of 17.5Bm3 are used instead, keeping the same excavator. Provide all
required steps, and comment on the results. There is no need to submit charts or
the site form for this part of the task.
Submission:
Include a written summary of your findings, detailing the basic steps you followed to ar
Travel time through curves with different length and radius.
Travel time at different total resistance and ground structure - Volvo A25D, unloaded.
Jotal resistence
Travel time at different total resistance and ground structure - Volvo A30D, loaded
bod resstrice
Groud stucmerive at your answers.
Submit your work to D2L by Sun, Oct 6th,2024, before 11:59 PM (Midnight).
Ensure your submission is neat and well-organized. Upload the completed assignment to the D2L Dropbox in PDF format. The filename should include your name, e.g., Assg1_YourName.
Marks will be allocated based on the accuracy of your solution and the professional presentation of your work, including comments and graphs that demonstrate your engineering judgment.
Travel time at rifferent that resistanes and nme ind strietime - Volun ????25n Inarled
A mining company is planning to develop an open -

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!