Question: A Monte Carlo analysis performed using tools like Crystal Ball is likely to directly provide which of the following for a project? Question 15 options:

A Monte Carlo analysis performed using tools like Crystal Ball is likely to directly provide which of the following for a project? Question 15 options: Stakeholder levels of satisfaction with a project Activities which are highly likely to have insufficient resources available The most expensive project activities or resources The likelihood of a project completing in the time-frame suggested by the project's critical path