Question: A Moving to another question will save this response. Question 23 A network of activities in a project has five activities as follows: Activity Precedence

A Moving to another question will save this

A Moving to another question will save this response. Question 23 A network of activities in a project has five activities as follows: Activity Precedence Duration (days) AF 5 12 CATEG15 DB, C 10 ED 20 Assuming the activities are completed as per the above durations, what is the earliest time activity D can be started? O 17 days O 5 days 20 days 30 days A Moving to another question will save this response