Question: A Moving to another question will save this response. Question 11 (CH6) Analogous estimating of an activity or project duration relles on a. estimating the

A Moving to another question will save this
A Moving to another question will save this response. Question 11 (CH6) Analogous estimating of an activity or project duration relles on a. estimating the duration of individual activities then combining them to come up with the duration of the whole project b. reserves allocated in the project schedule c. historical data from a similar activity or project d. identifying the early start, early finish, late start, and late finish of each activity A Moving to another question will save this response. MacBook Air