..) A Moving to the next question prevents changes to this answer. Question 30 of 3 Question 30 2 points Save Answ If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost variance (CV)? O 350 0-75 O 400 O -50