Question: A ( n ) _ _ is a relationship between one or more project activities Group of answer choices discretionary dependency mandatory dependency external dependency

A(n)__ is a relationship between one or more project activities
Group of answer choices
discretionary dependency
mandatory dependency
external dependency
internal dependency
project dependency