Question: A. Need help drawing a network diagram and identifying a critical path based on this information. B. Then activity E has taken 8 weeks past

A. Need help drawing a network diagram and identifying a critical path based on this information.
B. Then activity E has taken 8 weeks past its anticipated duration to complete, what will happen to the projects schedule,how will the duration change, and Is there a new critical path?
Immediate Predecessor(s) Activity A B D E F G Optimistic 1 2 3 6 4 6 2 Time Estimates (week) Most Likely Pessimistic 4 7 6 10 3 9 13 14 6 14 8 16 5 8 B A AC B D, E, FStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
