Question: A. Need help drawing a network diagram and identifying a critical path based on this information. B. Then activity E has taken 8 weeks past

A. Need help drawing a network diagram and

A. Need help drawing a network diagram and identifying a critical path based on this information.

B. Then activity E has taken 8 weeks past its anticipated duration to complete, what will happen to the projects schedule,how will the duration change, and Is there a new critical path?

Immediate Predecessor(s) Activity A B D E F G Optimistic 1 2 3 6 4 6 2 Time Estimates (week) Most Likely Pessimistic 4 7 6 10 3 9 13 14 6 14 8 16 5 8 B A AC B D, E, F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!