Question: A. Network design Activity B. Prepare data for transfer C. Order and delivery of IT servers and required supports D. Install supports for servers
A. Network design Activity B. Prepare data for transfer C. Order and delivery of IT servers and required supports D. Install supports for servers E. Order and delivery of electrical equipment and cables F. Install electrical equipment G. Install cables H. Check power supply I. Install servers J. Check reliability of new infrastructure K. Obtain approval from senior management L. Inform and train employees M. Finalize data transfer to new network Immediate Duration predecessors (days) 14 A 20 A 10 C 10 A 12 D, E 5 F 7 G 1 H 7 B, I 4 J 3 J 6 K, L 6