Question: A network has been crashed to the point where all activities are critical. Additional crashing OA . can be done, but all critical tasks must
A network has been crashed to the point where all activities are critical. Additional crashing OA can be done, but all critical tasks must be reduced in duration. O B may require crashing multiple tasks simultaneously O C is prohibitively expensive. O D is impossible E is unnecessary.