Question: A network has been crashed to the point where all activities are critical. Additional crashing: a. is unnecessary b. is prohibitively expensive c. can be

A network has been crashed to the point where all activities are critical. Additional crashing:

a.

is unnecessary

b.

is prohibitively expensive

c.

can be done but all critical activities must be reduced in duration

d.

is impossible

e.

may require crashing multiple activities simultaneously