Question: A new business project includes work packages A,B and C. What is the expected EMV of the entire project given the following: - Work package

A new business project includes work packages A,B

A new business project includes work packages A,B and C. What is the expected EMV of the entire project given the following: - Work package A has a schedule overrun risk probability of 10% with an impact of $10,000. - Work package B has a cost under-run risk probability of 25% with an impact of $10,000. - Work package C has a new resource learning curve risk impact of $15,000 a. (+) $5,000 b. ()$5,000 c. (-) $13,500 d. (+)$7,250