Question: A new equipment was installed, and we estimate this learning curve percentages. The cost of labor per unit is $1. The Weekly capacity is


A new equipment was installed, and we estimate this learning curve percentages. The cost of labor per unit is $1. The Weekly capacity is 8655 units. Determine the labor learning cost for this equipment. Week 1 LC% 30% 2 60% 3 70% 4 80% 5 90% 6 100%
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
Week 1 Cost 30 x 8655 x 1 259650 Week 2 Cost 60 x 8655 x 1 519... View full answer