Question: A new order filling system needs to be installed as soon as possible. The following table lists the projects activities and their predecessors. Also provided

A new order filling system needs to be installed as soon as possible. The following table lists the projects activities and their predecessors. Also provided is the cost information to reduce the standard activity times. Set up and solve an LP model using Excel to crash this project to 24 weeks. What is the total crashing cost?

Activity

Immediate Predecessors

Standard Time (WKS)

Standard Cost

Crash Time (WKS)

Crash Cost

A

-

7

$2000

5

$3500

B

A

10

$3000

8

$4700

C

A

8

$3400

7

$3700

D

C

6

$1600

4

$2600

E

C

7

$1900

4

$4000

F

D, E

5

$1200

3

$2800

G

B, C

11

$8200

8

$10900

H

F, G

4

$2600

3

$3800

A new order filling system needs to be installedPLEASE USE TEMPLATE ABOVE. THANK YOU.

TA T. TO Start Start Start A B C . . Start Start Start Start Start D E F G H CAC Crash Crash A B C C Crash Crash D C Crash E C Crash F Co Crash G C Crash H Solution value Crash cost Constraints: AB A-> B-> C->G C->D C-E DF EPF FSH G H Crash limit A Crash limit B Crash limit Crash limit D Crash limit E Crash limit F Crash limit G Crash limit H Project finish LHS Sign RHS Crash project to weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!