Question: A new product development project requires at least 3 0 worker days to complete. Assume no task requires more than one human resource, and the

A new product development project requires at least 30 worker days to complete. Assume no task requires more than one human resource, and the tasks can be completed independently of each other.
What is the shortest time estimate for completion if the project is constrained to two workers per day?
Group of answer choices
15 days
16 days
7 days
30 days
none of the given options is correct