Question: A new product is under development. The product will be manufactured in batches. The first batch is expected to take 2,000 labour hours to

 A new product is under development. The product will be manufactured in 

A new product is under development. The product will be manufactured in batches. The first batch is expected to take 2,000 labour hours to manufacture. There will be a 95% learning curve that will continue until 48 batches have been produced. Calculate the expected time required to produce the 48th batch of this new product.

Step by Step Solution

3.59 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer Calculate the expected time required to produce 48 th batch Answer Expected time for 48 th batch is 3132 hours Working We use Wrights law of le... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!