Question: A new project manager is assigned to a high - volatility project. The project manager starts with the requirements analysis process. Who should the project

A new project manager is assigned to a high-volatility project. The project manager starts with the requirements analysis process.
Who should the project manager onboard to assist with the requirements traceability matrix or analysis?
A. Technical consultant
B. Business analyst
C. Project sponsor
D. Systems analyst
O?
Previous
Next
Clear
Flag