Question: A new project manager is assigned to a high - volatility project. The project manager starts with the requirements analysis process. Who should the project
A new project manager is assigned to a highvolatility project. The project manager starts with the requirements analysis process.
Who should the project manager onboard to assist with the requirements traceability matrix or analysis?
A Technical consultant
B Business analyst
C Project sponsor
D Systems analyst