Question: A new scientific research centre has been constructed using the NEC 4 Engineering and Construction Contract main Option E . The Project Manager certifies Completion

A new scientific research centre has been constructed using the NEC4 Engineering and Construction Contract main Option E. The Project Manager certifies Completion on 01 May. The defects date is 52 weeks after Completion of the whole of the works. The defect correction period is 4 weeks.
Question 10
On 01 August in the same year the Supervisor informs the Project Manager that the air conditioning systems are providing 12 air changes per hour. The matter was discussed during a walk round of the buildings with the Contractor. The Scope provided by the Client requires 14 air changes. The Scope provided by the Contractor for its design states all air conditioning systems will be designed to operate at 12 air changes per hour.
Which ONE of the following statements is correct?
Select ONE option
The Contractor could make a proposal to the Project Manager for changing the Scope so the Defect does not have to be corrected.
Completion has been certified so it is too late to notify a Defect.
The Project Manager should instruct the Supervisor to notify the Contractor of a Defect
The matter is not a Defect as the number of air changes complies with the Scope provided by the Contractor for its design.
The Project Manager should notify the Contractor of a Defect.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!