Question: A new sports complex is being constructed using the NEC 4 Engineering and Construction Contract main Option D , secondary Option X 1 , X
A new sports complex is being constructed using the NEC Engineering and Construction Contract main Option D secondary Option X X and X The Client is responsible for the design. The access date for section of the works is July. The period for reply is three weeks.
Question
The latest Accepted Programme shows the date on which the Contractor needs access to section as July. On July the Contractor informs the Project Manager that they will in fact be ready to start work on section on the access date and will require access by this time. The Project Manager telephones the Contractor that the Client will not be able to allow access by the access date.
Which TWO of following statements describe the best course of actions for the Project Manager?
Select TWO options
The Project Manager should notify the Contractor of a compensation event and give an instruction to the Contractor to submit a quotation
The Project Manager should notify the Contractor of a compensation event but not give an instruction to the Contractor to submit a quotation as the event has arisen from a fault of the Contractor when showing a later date for access on the programme
The Project Manager should notify the Contractor of an inconsistency between the Contract Data and the Accepted Programme and resolve the inconsistency by giving an instruction to the Contractor to submit a revised programme showing the correct date for access
The Project Manager should inform the Client of the matter
The Project Manager should notify the Contractor of an early warning as the matter could delay Completion
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock