Question: A office space construction project has the following work breakdown: Activity Predecessor Most Likely Optimistic Pessimistic Normal Cost Crash Cost A -- 5 3 8

A office space construction project has the following work breakdown:

Activity

Predecessor

Most Likely

Optimistic

Pessimistic

Normal Cost

Crash Cost

A

--

5

3

8

400

800

B

--

7

5

11

600

900

C

--

5

3

8

300

700

D

A

10

7

15

800

1100

E

B

6

3

10

500

900

F

A,C

8

4

12

1000

1500

G

B

4

4

4

500

500

H

E, F

7

7

7

800

800

I

E,F,D

4

2

8

400

700

J

H

6

3

9

600

1200

Using the three time estimates (and assuming the critical path), what is the risk that this project does not get completed within 30 days?

If we assume that penalty costs will apply a rate of $650 per day and indirect costs are $300 per day and a deadline of 20 days, what would be the most cost effective way to reduce this project 2 days in duration from its original completion time? Assume that the most likely times are the normal times and the optimistic times are the crash times. Indicate which activities would be crashed and how much money would be saved in the process.

Assuming the same conditions as in b, what would be the overall minimum cost schedule assume that the deadline is actually 20 days to get the project done?

What would be the shortest feasible way to get this project done if budget didnt matter?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!