Question: A one-week delay occurs during project execution. The project manager identifies that authorizing overtime will regain the time lost. However, project management office (PMO) policies

A one-week delay occurs during project execution. The project manager identifies that authorizing overtime will regain the time lost. However, project management office (PMO) policies prohibit overtime. What should the project manager do?

A. Submit a change request

B. Hire additional resources

C. Inform the project team of the delay

D. Update the project schedule