Question: ( a ) Overall project's BCWS = 1 0 0 + 5 0 + 5 0 + 7 0 + 9 0 + 4 0

(a)
Overall project's BCWS =100+50+50+70+90+40+50=450 thousand
Overall project's BCWP =100+50+50+0+90+0+50=340 thousand
Overall project's ACWP =100+55+40+0+140+0+25=360 thousand
So,
Cost Performance Index (CPI)= BCWP / ACWP =340/360=0.944 which is less than 1.0. Therefore, the project is running overbudget.
Schedule Performance Index (SPI)= BCWP / BCWS =340/450=0.756 which is less than 1.0. Therefore, the project is delayed.A
Subtasks
Cost status
Schedule status
1
1
H
CPI
= BCWP/ACWP
=C2/D2
=C3/D3
=C4/D4
32
43
B
C
D
E
BCWS
BCWP
ACWP
SV
= BCWP -
Subtasks BCWS BCWP ACWP SV
= BCWP - BCWS CV
= BCWP - ACWP SPI
= BCWP/BCWS CPI
= BCWP/ACWP Cost status Schedule status
1100100100001.001.000 As per budget As per schedule
25050550-51.000.909 Overbudget As per schedule
35050400101.001.250 Underbudget As per schedule
47000-7000.00- As per budget Delayed
590901400-501.000.643 Overbudget As per schedule
64000-4000.00- As per budget Delayed
75050250251.002.000 Underbudget As per schedule
8000------
Total 450340360-110-200.7560.944 Overbudget Delayed
(b)
BAC =579 thousand
The Estimated Cost at Completion (EAC)= BAC / CPI =579/0.944=613 thousan

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!